zozen boiler
HomeCasesGas-fired boilers cases4-Ton Condensing Gas-Fired Steam Boiler Project for the Chemical Industry

4-Ton Condensing Gas-Fired Steam Boiler Project for the Chemical Industry

Gas-fired boilers cases
Chemical industry
  • Type

    Steam

  • Capacity

    4 tph

  • Location

    Guangdong, China

  • Model

    NWNS4-1.25-Q

4-Ton Condensing Gas-Fired Steam Boiler Project for the Chemical Industry
Case introduction

In the production process of composite board adhesive, stable steam is required for reactor heating, raw material insulation, and process temperature control. For adhesive production enterprises, a gas-fired steam boiler not only provides thermal energy, but also affects batch consistency, production continuity, and operating cost control.

Recently, ZOZEN Boiler supplied a 4 t/h NWNS series condensing gas-fired steam boiler to a composite board adhesive manufacturer in Guangdong, providing stable steam support for its production line.

For the composite board adhesive industry, stable steam pressure and temperature have a direct impact on production rhythm. Based on the customer’s steam demand and process characteristics, ZOZEN Boiler designed a suitable gas-fired steam boiler system, including the combustion system, control system, water treatment system, economizer, and other auxiliary equipment, so that boiler operation could match production-side requirements.

Considering the fast production pace and clear project schedule requirements of enterprises in Guangdong, ZOZEN Boiler focused on delivery planning and technical communication during project implementation, helping the customer move the boiler project forward smoothly. For gas-fired steam boiler users, ZOZEN Boiler can also provide boiler system solutions according to gas supply conditions, steam pressure requirements, and workshop layout.

Customer feedback—— A new materials company in Guangdong

After the boiler was put into operation, the steam supply has remained relatively stable, and the level of automation meets our workshop management requirements. The condensing energy-saving configuration is helpful for controlling gas costs during long-term operation. Overall, the operating experience is in line with our expectations. During the project, ZOZEN Boiler’s technical team communicated in a timely manner and provided specific suggestions on boiler room layout, auxiliary equipment configuration, and commissioning.

PreviousExport to Brazil: ZOZEN ASME Certificated 4 t/h Biomass Gas-Fired Steam Boiler Project NextEnd