What are precautions of banking-up operation of coal-fired steam boiler?

07 Aug 2020

When regulating and controlling the coal-fired steam boiler, it will involve the banking-up operation which has a set of operating steps and points for attention. Strictly adhering to the operating steps will be helpful for the more efficient operation of coal-fired steam boiler and can extend its service life at the same time.

First of all, we should properly reduce the load of coal-fired steam boiler by gradually thickening the coal layer according to the planned time of blowing out the furnace. Please notice that the thickness of coal layer can not exceed 200 mm. Meanwhile, we should properly accelerate the grate speed to push the banking-up process.

When the coal layer of steam boiler is thickened to about 1 mm from the slag stopper, we can shut down the grate, forced draft fan, induced draft fan and adjust the regulator damper and flue damper which can control the air supply to the appropriate position.

At this time, the steam boiler relies on natural ventilation to maintain coal's weak combustion, which is used for sewage discharge, so the boiler's water level will rise to a high but allowable level. If the fire burns out the coal gate, we can restart the grate and move the coal back for a certain distance.

After a period of shutdown, if the steam boiler needs to resume operation, we just need to start the forced draft fan, induced draft fan and adjust the opening of regulator damper and flue damper. When the boiler burning turns normal, we can adjust the coal layer and start the grate to resume the operation of boiler.

These are the banking-up operating steps, points for attention and operating steps to resume boiler's operation.

Related FAQs View More
Related news View More
  • Energy Costs and Stable Steam Supply Draw Attention as ZOZEN Boiler Provides Diverse Steam Solutions for Textile Enterprises Worldwide
    From spinning and weaving to dyeing, printing and heat setting, steam is required throughout multiple stages of textile production. As textile enterprises pay closer attention to energy costs, steam supply stability and emission requirements, boiler selection can no longer be based solely on rated evaporation capacity. Local fuel availability, production load, boiler room conditions and ongoing operation and maintenance also need to be considered. Recent textile projects served by ZOZEN Boiler ...
    10 Nov 2026
  • ZOZEN Boiler Supports Building Materials Projects in Hubei with Steam and Thermal Oil Solutions
    IntroductionIn Wuhan, Hubei Province, Hubei Hanjia New Materials Co., Ltd. and Wuhan Yiqingsheng Building Materials Co., Ltd. required thermal energy equipment for autoclave curing and continuous production-line heating, respectively. Based on the production processes, fuel conditions and site requirements of the two companies, ZOZEN Boiler supplied an 8 t/h DZL series biomass steam boiler and a 7.2-million-kcal YWW series biomass thermal oil boiler. The two projects use different heat-transfer ...
    03 Nov 2026
  • ZOZEN Gas-Fired Steam Boiler Marks Five Years of Service at Guizhou Haocaitou, Supporting Food Production
    At Guizhou Haocaitou Food Co., Ltd. in Tongren, Guizhou Province, a ZOZEN WNS series gas-fired steam boiler has been operating for five years as part of the company’s steam supply system. The WNS10-1.25-Q boiler, with a rated capacity of 10 t/h, serves as an important heat source for food production. In recent feedback, the customer noted that matching the equipment configuration to production requirements, along with ease of daily operation and maintenance, were key considerations when se...
    27 Oct 2026

Find the Right Boiler For You

Name *

Email *

WhatsApp/WeChat

Products

Power/Capacity