What factors can cause carryover of boiler water into the steam system?
If the impurities in the boiler feedwater are not dealt with properly, carryover of boiler water into the steam system can occur.
Carryover can be caused by two factors:
1.Priming - This is the ejection of boiler water into the steam take-off and is generally due to one or more of the following:
1) Operating the boiler with too high a water level.
2) Operating the boiler below its design pressure; this increases the volume and the velocity of the steam released from the water surface.
3) Excessive steam demand.
2.Foaming - This is the formation of foam in the space between the water surface and the steam off-take. The greater the amount of foaming, the greater the problems which will be experienced.
-
SZL series biomass-fired hot water boilerLive Chat4.2-17.5 MW1-1.25 MPa
-
DZL series coal-fired hot water boilerLive Chat1.4-7 MW0.7-1.25 MPa
-
SZS series gas-fired (oil-fired) hot water boilerLive Chat7-116 MW1-1.6 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat
-
On the thriving industrial land of Shandong, the continuous demand for thermal energy supply from enterprises drives the transformation of the boiler industry. With profound technical expertise and ongoing innovation, ZOZEN Boiler remains at the forefront of providing high-quality, adaptable boiler models for various industries. ZOZEN Boiler Provides Tailored Boiler Solutions for Shandong Industries Looking back, the cooperation projects with Shandong Luhua Group and Shandong...29 Jul 2025
-
In the industrial zone of Wen’an County, Xinghua Cable Co., Ltd. is making steady progress on its project with an annual production capacity of 11 million meters of wires, cables, and accessories, backed by an investment of RMB 520 million. Upon completion, the project is expected to create over 150 jobs and generate annual sales revenue of RMB 800 million, demonstrating promising prospects. As a key supplier of thermal energy equipment, ZOZEN Boiler is quietly supporting the development o...22 Jul 2025
-
On March 20, 2025, the Guizhou Jinyuan Zhijin “Replacing Small Units with Large Ones” Relocation Project (2×660 MW), under State Power Investment Corporation, successfully achieved the first ignition of its boiler. This project replaced traditional oil-fired ignition fuel with liquefied natural gas (LNG), setting a new precedent for employing clean energy in 660 MW ultra-supercritical “W” flame boilers. As a key equipment supplier for this project, ZOZEN Boiler prov...15 Jul 2025