What is the inspection process before coking and boiling?
Before coking and boiling, check boiler parts detailedly. Inspection items are as follows:
1. Before coking and boiling, chain grate should be cold test run again and continuous running time shall not be less than 24 hours.
2. Ignition door can be opened flexibly, coal gate can be lift and dropped conveniently, coal gate left and right side is of the same distance to grate, and ensure the material layer thickness on both sides of the furnace is equal. If distance is not equal, it can be adjusted by the adjusting bolt. Cover plate on coal gate should be covered tightly to avoid coal gate stuck
caused by sundries leaked in.
3. Control damper of each air chamber in grate and flue gas damper switch in gas flue duct shall be flexible.
4. Auxiliaries such as FD fan, ID fan, slag extractor, feedwater equipment and so on shall cold test run normally.
5. Check if manholes, handholes are tight and if the accessory parts are complete.
6. Check if furnace wall is normal and if smoke chamber is sealed tightly.
7. Check if steam piping, feedwater piping and blowdown piping are complete and unblocked.
8. Check if economizer and air pre-heater are tight and if flue gas duct is unblocked.
9. Lubricating oil shall be full filled in all bearing boxes and oil cups.
10. Check if duct collector interface is tight and if there's air leakage of ash discharge valve.
-
SZL series biomass-fired steam boilerLive Chat6-35 t/h1-2.5 MPa
-
DZL series biomass-fired steam boilerLive Chat2-10 t/h1-2.5 MPa
-
DHL series biomass-fired steam boilerLive Chat20-75 t/h1.25-5.4 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
Industrial heating upgrades can have a direct impact on a factory’s production schedule and operational stability. For manufacturers investing in new facilities or upgrading equipment in Vietnam, boiler selection involves more than fuel costs. Process temperatures, continuous heat supply, emission requirements, and long-term maintenance must all be taken into account. Whether transitioning from coal to natural gas or biomass, manufacturers need a heating solution tailored to their actual p...17 Nov 2026 -
From spinning and weaving to dyeing, printing and heat setting, steam is required throughout multiple stages of textile production. As textile enterprises pay closer attention to energy costs, steam supply stability and emission requirements, boiler selection can no longer be based solely on rated evaporation capacity. Local fuel availability, production load, boiler room conditions and ongoing operation and maintenance also need to be considered. Recent textile projects served by ZOZEN Boiler ...10 Nov 2026 -
IntroductionIn Wuhan, Hubei Province, Hubei Hanjia New Materials Co., Ltd. and Wuhan Yiqingsheng Building Materials Co., Ltd. required thermal energy equipment for autoclave curing and continuous production-line heating, respectively. Based on the production processes, fuel conditions and site requirements of the two companies, ZOZEN Boiler supplied an 8 t/h DZL series biomass steam boiler and a 7.2-million-kcal YWW series biomass thermal oil boiler. The two projects use different heat-transfer ...03 Nov 2026