What is the installation process of burner of ZOZEN's gas-fired boiler?
1. Burner should be installed in accordance with requirements of burner installation and operation manual.
2. Burner should be installed in the center of the reserved front wall hole, the embeded length should comply with the design requirements and the fixation should be reliable.
3. Burner center deviation shall not be more than +2mm and air adjustment actuator should be flexible.
4. Burner and boiler body junction surface should be sealed reliably, the position that needed to be sealed between burner and burner installation cylinder should be installed and sealed according to drawings strictly so as to prevent damage to burner caused by flue gas flowing back.
-
WNS series gas-fired (oil-fired) steam boilerLive Chat1-20 t/h0.7-2 MPa
-
SZS series gas-fired (oil-fired) steam boilerLive Chat2-110 t/h1.25-5.3 MPa
-
WNS series gas-fired (oil-fired) hot water boilerLive Chat0.7-14 MW0.7-1.25 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat
-
With the ongoing advancement of the “Belt and Road” Initiative, economic and trade cooperation between China and Kyrgyzstan has become increasingly close. In February 2025, the two countries announced the launch of negotiations on a service trade and investment agreement, injecting new momentum into their bilateral collaboration. Against this backdrop, Chinese industrial equipment is making its way into Kyrgyzstan, helping local businesses grow—ZOZEN Boiler stands out as an exe...10 Jun 2025
-
ZOZEN Boiler Showcases Multi-Dimensional Energy Solutions at Serbia’s TOPS 2025 Scientific SymposiumFrom June 2 to June 3, 2025, the TOPS 2025 Scientific Symposium, hosted by the Serbian Heating Association, was held in grand fashion. As one of the most influential events in the European heating industry, it attracted leading international brands such as Weishaupt, Bosch, and KSB, with a collective focus on cutting-edge technologies in gas and biomass boilers. In light of rising energy costs, biomass boilers, with their outstanding cost-saving potential, became a hot topic of discussion. As th...11 Jun 2025
-
On May 29, 2025, the three-day Russia Heating Exhibition (HEAT&ELECTRO MACHINERY) successfully concluded at the Timiryazev Center in Moscow. As a prestigious professional exhibition for thermal and electric power equipment, this year’s event attracted 150 high-quality enterprises and over 8,000 professional visitors from around the world. ZOZEN Boiler, in collaboration with Manto Chemistry, showcased a range of high-efficiency and environmentally friendly boiler products, demonstrating...03 Jun 2025