1. After boiler body, economizer, air pre-heater, dust collector, etc are in place and installed, connect FD fan, ID fan, etc according to drawing and then connect corresponding flue gas duct. After fan in place, alignment between foundation and equipment base should be conducted with parallels. Fan position alignment should center on a shaft, central elevation deviation and vertical and lateral central line positional deviation should be 10mm or less and fan spindle should be in level state. Th...
The flue gas treatment of biomass boiler adopts the pretreatment and deep processing. The deep processing adopts the pulsed jet cloth filter, the waste gas treated by this system can meet the discharge standard stably. The flue gas enters the cyclone dust collector or flame arrestor through the dust removal pipeline.
Fuel injection nozzle of combustion oil pump of gas boiler does not inject fuel. Possible causes include blockage and leakage of oil supply pipeline. The solution is to clean, repair or replace;
Mechanical dust remover is a device that separates dust particles from airflow by using mass forces (such as gravity, inertial force and centrifugal force). Such as gravity dust remover, inertial dust remover and cyclone dust remover. Mechanical dust remover is characterized by simple structure, low cost and convenient maintenance, but its dust removal efficiency is low.
Different boiler parameters have different requirements on the PH value of boiler water. Generally speaking, the PH value of boiler water is basically between 10 and 12, in some cases, the PH value is between 9 and 11.
The gas-fired boiler is operated by an advanced combustion machine, equipped with automatic gas supply and ignition combustion system, and the gaseous fuel is easy to burn. Therefore, the gas-fired boilers need not be equipped with blower and induced draft fan components.
Make-up water rate refers to the proportion of treated water added to the boilers, steam turbine equipment and its thermal systems and participating in the circulation of steam-water systems in the boiler steam volume in the calculation period.
Prepare relevant technical data, including technical data of boiler manufacture and installation, boiler use registration data, boiler operation records, water quality test records, repair and modification records, accident records and previous inspection reports;