System load is measured in either BTUs or tons of steam (at a specific pressure and temperature). It would be nearly impossible to size and select a boiler(s) without knowing the system load requirements. Knowing the requirements leads to the following information:
The boiler(s) capacity, taken from the maximum system load requirement.
The boiler(s) turndown, taken from the minimum system load requirement.
Conditions for maximum efficiency, taken from the average system load requirement.
Determining the total system load requires an understanding of the type(s) of load in the system. There are three types of loads: heating, process, and combination.
Stack temperature is the temperature of the combustion gases (dry and water vapor) leaving the boiler. A well-designed boiler removes as much heat as possible from the combustion gases. Thus, lower stack temperature represents more effective heat transfer and lower heat loss up the stack. The stack temperature reflects the energy that did not transfer from the fuel to steam or hot water. Stack temperature is a visible indicator of boiler efficiency. Any time efficiency is guaranteed, predicted stack temperatures should be verified.
Stack loss is a measure of the amount of heat carried away by dry flue gases (unused heat) and the moisture loss (product of combustion), based on the fuel analysis of the specific fuel being used, moisture in the combustion air, etc.
The primary purpose of the boiler is to supply energy to the facility's operations – for comfort heating, manufacturing process, laundry, kitchen, etc. The nature of the facility's operation will dictate whether a steam or hot water boiler should be used. Hot water is commonly used in heating applications, with the boiler supplying water to the system at 120°F to 220°F. The operating pressure for hot water heating systems usually is 30 psig to 125 psig (hydrostatic). Under these conditions, there is a wide range of hot water boiler products available. If system requirements are for hot water of more than 250°F, a high-temperature water boiler should be considered.
Package boiler is a boiler that had been fabricated and available as a complete package. The entire pressure parts have been assembled in the workshop and ready to be sent to the field or site where power plant is located. On the field/site requires only connection and integration of course work in electrical connections, water pipes, steam pipes and fuel piping system to operate. Package boiler is one of classification of boiler based on erection. Design package boilers in general are the type of Fire Tube Boiler and have made up shell and tubes. This type has high heat transfer both radiation and convection.
The combustion air preheater is definitely one of heat exchanger applications. Based on Figure 1 below, flue gas simply leaves steam boiler and passes via air preheater. The combustion air is passed through this equipment too to increase its temperature before being combined with boiler fuel.
Because the temperature of combustion air is lower than the temperature of flue gas, combustion air receive heat transfer from flue gas through combustion air preheater in the process of convection heat transfer. The heat transfer make temperature of flue gas lower and consequently minimizes its heat loss and also decreases the air temperature to stack.
Economizer is one of steam boiler’s equipment which is used to heat feedwater before it is supplied into steam drum. Economizer is the heat exchanger equipment to increase boiler efficiency by absorbing heat recovery of flue gases. The lower temperature of flue gas out from stack, the heat loss will be less and the fuel which is needed to convert water into steam will be also less in certain circumstances. So it can be said that economizer can save the fuel efficiently. Economizer will make temperature of feedwater higher, so steam boiler can produce steam easily.
Evaporation phase occurs in water wall tubes. Evaporation is the process to convert water into steam. Therefore water wall tubes should be designed and constructed to provide high heat absorption, minimum excess air level and highest boiler efficiency. Construction of water wall tubes should be also constructed to prevent air leakage into steam boiler, eliminate amount of heat losses and permit high heat release and combustion rate in the furnace.
Construction of water wall tubes must provide high quality of the supporting component such as tubes, casing, refractory, lagging, tile, fin, and so on. Best construction will reduce heat loss and maintenance. Construction of water wall tubes can be classified into four types such as:
In a boiler, energy from the fuel is transferred to liquid water in order to create steam. Once the water is heated to boiling point, it is vaporized and turned into saturated steam. When saturated steam is heated above boiling point, dry steam is created and all traces of moisture are erased. This is called superheated steam.