What are the reasons for insufficient burning in the coal chain grate boilers?
The first reason is unreasonable structural design.
In the operation of chain grate boiler, uneven distribution of short coal seams in grate, improper adjustment of coal feeder, unreasonable control of coal seams and poor regulation performance of air supply volume in air chamber will all lead to insufficient burning of coal.
The second reason is unreasonable setting of secondary air.
If the primary wind speed is too high, the air volume is too large, and the air rate is too large, the pulverized coal concentration is obviously low, and insufficient preheating will cause the ignition point of pulverized coal to increase, and successive flames cannot be formed. Improper selection of secondary air distribution will greatly reduce the flame temperature.
The third reason is coal quality.
The basic requirements of the boiler for fuel are very high. The coal with the particle size of 25mm-40mm is less than 30%, the large particle size is less than 40mm, the moisture is 12%-20%, the volatile matter is greater than 18%, the calorific value is greater than 4200 kcal/kg, and the ash melting point is not lower than 1100℃. If the ash content in coal increases and the evaporation content is low, it is not conducive to the dispersed combustion of pulverized coal.
-
DZL series coal-fired steam boilerLive Chat2-10 t/h1-2.5 MPa
-
SZL series coal-fired steam boilerLive Chat6-35 t/h1-2.5 MPa
-
DHL series coal-fired steam boilerLive Chat20-75 t/h1.25-5.4 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
Behind industrial manufacturing often lies an invisible thermal energy lifeline. Whether boiling syrup, synthesizing chemical materials, or pressing new energy security materials, every physical and chemical change on the production line has strict requirements for the temperature, pressure, and continuity of thermal energy. When green biomass energy enters these vastly different manufacturing workshops, how can various forms of pellets, wood blocks, or straw be converted into the "precise temp...08 Sep 2026 -
Recently, a special equipment inspection team visited Wuxi Zozen Boilers Co., Ltd. for an inspection and guidance session. Mr. Zhang Guoping, General Manager of ZOZEN Boiler, together with representatives from relevant departments, participated in the inspection and discussions. The meeting focused on special equipment production quality management, the implementation of safety responsibilities, manufacturing process control, and documentation management. Special Equipment Inspection Team Con...25 Aug 2026 -
At a local paper manufacturing company in Egypt, a ZOZEN WNS Series 6 t/h gas-fired steam boiler has been supplied as part of an export project. The Egyptian paper mill uses natural gas as the boiler fuel to meet the process steam requirements of paper production. The project also includes technical documents and a product solution prepared in accordance with ASME and CE certification requirements. Paper manufacturing is a continuous industrial process. Steam is involved in several stages, incl...01 Sep 2026