What are the correct ignition procedures for industrial coal-fired boilers?
The ignition of industrial coal-fired boiler needs to be operated steps by steps, and the ignition operation is different according to the specific model of industrial coal-fired boiler. Grates of industrial coal-fired boilers are usually divided into manual grates and mechanical grates. Here, according to the different grates, the correct ignition steps of industrial coal-fired boilers are introduced in detail.
Ignition steps of manual grate industrial coal-fired boiler:
The materials required for ignition include combustible materials (for ignition), firewood (for transition) and coal.
- First of all, combustible materials and firewood are stacked on the grate and laid flat in front of the grate to ignite combustible materials and firewood.
- Then wait for the firewood to burn and throw a small amount of coal on the fire by manual or mechanical means (first use small particles of coal).
- After the coal burns, gradually move the fire around the grate, and then spread the coal over the entire grate. The entire ignition process is finished.
Ignition steps of mechanical grate industrial coal-fired boiler:
The ignition area of the grate is located between the rear arch of the arched bucket and the coal gate. Combustibles, firewood and coal are laid in layers in the ignition area, with coal at the bottom and combustible and firewood at the top.
- Ensure that the negative pressure in the hearth of the coal-fired boiler is between 15pa and 30pa, turn on the induced draft fan of the boiler, and start ignition.
- Ignite the upper fuel, wait for the upper fuel to burn stably, and then slowly rotate the grate to advance about 0.8 meters.
- Wait for the bottom coal to burn. When the coal is burning, open the east grate and start the boiler blower to increase the coal transportation. According to the combustion condition of coal, open the baffles of each part of air chamber.
-
SZL series coal-fired steam boilerLive Chat6-35 t/h1-2.5 MPa
-
SHX coal-fired CFB (circulating fluidized bed) steam boilerLive Chat10-35 t/h1.25-2.5 MPa
-
DHL series coal-fired steam boilerLive Chat20-75 t/h1.25-5.4 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
From May 6 to 7, 2026, PALMEX JAKARTA 2026, the International Palm Oil Industry Equipment Exhibition, was held at JIEXPO in Jakarta, Indonesia. At booths 190 & 192, ZOZEN Boiler presented its boiler products and thermal energy solutions for industries such as palm oil processing. During the two-day exhibition, ZOZEN welcomed multiple groups of visitors, including existing clients and new prospects. Some new visitors returned to the booth several times for further discussions, and the overall...12 May 2026 -
ZOZEN Boiler has recently shipped a 10-ton WNS series heavy oil steam boiler to Ecuador, where it will support the production line of a local corrugated board packaging company. The project marks another step in ZOZEN’s expansion in Ecuador’s paper industry and reflects growing demand in South America for reliable steam supply, fuel adaptability, and after-sales support. ZOZEN WNS series heavy oil condensing steam boiler Stable steam supply matters in paper productionIn paper and...05 May 2026 -
From May 6 to 7, 2026, ZOZEN Boiler will participate in Palmex Indonesia 2026 at Jakarta International Expo (JIEXPO), Indonesia. ZOZEN Boiler will welcome visitors at Booth 190 & 192. As an industry event focused on the palm oil sector in Southeast Asia, the exhibition brings together companies involved in palm oil processing, supporting energy systems, and industrial equipment, offering ZOZEN Boiler a valuable opportunity to meet customers from Indonesia and surrounding markets. ZOZEN Bo...28 Apr 2026