What is the process and operation of low-pressure boiler furnace drying?
(1) The furnace drying time depends on the shape, structure and humidity of the furnace. It takes 4 ~ 7 days for small low-pressure boilers and 10 ~ 15 days for heavy furnace walls.
(2) First, bake with wood, on the ash hopper of the room furnace and the grate of the chain furnace, use small fire for natural ventilation within 2 ~ 3 hours. When the temperature of combustion chamber rises, the ventilation capacity will be improved, and the flue damper can be turned down a little. It is best to keep the exhaust temperature below 25℃ on the first day.
(3) The next day, the fire can be enlarged and placed in the center of the grate, and the water temperature in the boiler should not exceed 70℃. On the third day, coal is added to the fire, and it is gradually baked with coal.
(4) Starting from the fourth day, only use coal to burn, start the induced draft fan, increase the furnace temperature, and keep the negative pressure of the furnace at 5 ~ 10 Pa [0.5 ~ 1 mm H2O].
(5) The temperature of the low-pressure boiler should be slowly increased when drying, and the temperature rise should be controlled at 20 ~ 40℃ every day. The flame should be evenly distributed, and it should not lean on one side of the furnace wall or under the front or rear arch of the chain furnace. To prevent the chain grate from burning out, the chain grate should rotate regularly. The boiler water level should be kept at the lowest level during the furnace drying. Check frequently during furnace drying, and take remedial measures if cracks or pits are found.
-
WNS series gas-fired (oil-fired) skid-mounted hot water boilerLive Chat0.7-2.8 MW1.0 MPa
-
DZW series biomass-fired reciprocating grate steam boilerLive Chat15-35 t/h1.25 MPa / 1.6 MPa / 2.5 MPa
-
DZL series biomass-fired steam boilerLive Chat2-10 t/h1-2.5 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
Behind industrial manufacturing often lies an invisible thermal energy lifeline. Whether boiling syrup, synthesizing chemical materials, or pressing new energy security materials, every physical and chemical change on the production line has strict requirements for the temperature, pressure, and continuity of thermal energy. When green biomass energy enters these vastly different manufacturing workshops, how can various forms of pellets, wood blocks, or straw be converted into the "precise temp...08 Sep 2026 -
Recently, a special equipment inspection team visited Wuxi Zozen Boilers Co., Ltd. for an inspection and guidance session. Mr. Zhang Guoping, General Manager of ZOZEN Boiler, together with representatives from relevant departments, participated in the inspection and discussions. The meeting focused on special equipment production quality management, the implementation of safety responsibilities, manufacturing process control, and documentation management. Special Equipment Inspection Team Con...25 Aug 2026 -
At a local paper manufacturing company in Egypt, a ZOZEN WNS Series 6 t/h gas-fired steam boiler has been supplied as part of an export project. The Egyptian paper mill uses natural gas as the boiler fuel to meet the process steam requirements of paper production. The project also includes technical documents and a product solution prepared in accordance with ASME and CE certification requirements. Paper manufacturing is a continuous industrial process. Steam is involved in several stages, incl...01 Sep 2026