What is the process and operation of low-pressure boiler furnace drying?
(1) The furnace drying time depends on the shape, structure and humidity of the furnace. It takes 4 ~ 7 days for small low-pressure boilers and 10 ~ 15 days for heavy furnace walls.
(2) First, bake with wood, on the ash hopper of the room furnace and the grate of the chain furnace, use small fire for natural ventilation within 2 ~ 3 hours. When the temperature of combustion chamber rises, the ventilation capacity will be improved, and the flue damper can be turned down a little. It is best to keep the exhaust temperature below 25℃ on the first day.
(3) The next day, the fire can be enlarged and placed in the center of the grate, and the water temperature in the boiler should not exceed 70℃. On the third day, coal is added to the fire, and it is gradually baked with coal.
(4) Starting from the fourth day, only use coal to burn, start the induced draft fan, increase the furnace temperature, and keep the negative pressure of the furnace at 5 ~ 10 Pa [0.5 ~ 1 mm H2O].
(5) The temperature of the low-pressure boiler should be slowly increased when drying, and the temperature rise should be controlled at 20 ~ 40℃ every day. The flame should be evenly distributed, and it should not lean on one side of the furnace wall or under the front or rear arch of the chain furnace. To prevent the chain grate from burning out, the chain grate should rotate regularly. The boiler water level should be kept at the lowest level during the furnace drying. Check frequently during furnace drying, and take remedial measures if cracks or pits are found.
-
WNS series gas-fired (oil-fired) skid-mounted hot water boilerLive Chat0.7-2.8 MW1.0 MPa
-
DZW series biomass-fired reciprocating grate steam boilerLive Chat15-35 t/h1.25 MPa / 1.6 MPa / 2.5 MPa
-
DZL series biomass-fired steam boilerLive Chat2-10 t/h1-2.5 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
For many manufacturers with mature production experience in China, expanding capacity overseas or building a new factory abroad often starts with one key question: can the local infrastructure and energy supply support long-term operation? This is especially important in Africa. In many countries, raw materials such as timber are readily available, while conventional fuels like natural gas and diesel are often more expensive and less stable in supply. For plywood plants, this creates a practica...24 Mar 2026 -
From late 2025 to early 2026, forward-looking reports from the World Economic Forum (WEF) and other organizations indicated that despite significant growth in global renewable energy capacity in 2024, global carbon dioxide emissions still reached historical highs. Facing severe climate safety challenges, multiple countries globally have introduced stricter environmental policies to promote a green and low-carbon economic transition. In this macro context, energy conservation and emission reducti...17 Mar 2026 -
The vast land of Inner Mongolia is undergoing a profound green industrial transformation. From fine chemical parks in Wuhai to food processing bases in Hohhot, traditional high-energy-consumption production models are gradually shifting toward cleaner and lower-carbon operations. In this wave of industrial upgrading, Wuxi Zozen Boilers Co., Ltd. (hereinafter referred to as “ZOZEN Boiler”), a manufacturer with over 30 years of experience in industrial thermal equipment, has delivered ...10 Mar 2026