(1) The furnace drying time depends on the shape, structure and humidity of the furnace. It takes 4 ~ 7 days for small low-pressure boilers and 10 ~ 15 days for heavy furnace walls.
(2) First, bake with wood, on the ash hopper of the room furnace and the grate of the chain furnace, use small fire for natural ventilation within 2 ~ 3 hours. When the temperature of combustion chamber rises, the ventilation capacity will be improved, and the flue damper can be turned down a little. It is best to keep the exhaust temperature below 25℃ on the first day.
(3) The next day, the fire can be enlarged and placed in the center of the grate, and the water temperature in the boiler should not exceed 70℃. On the third day, coal is added to the fire, and it is gradually baked with coal.
(4) Starting from the fourth day, only use coal to burn, start the induced draft fan, increase the furnace temperature, and keep the negative pressure of the furnace at 5 ~ 10 Pa [0.5 ~ 1 mm H2O].
(5) The temperature of the low-pressure boiler should be slowly increased when drying, and the temperature rise should be controlled at 20 ~ 40℃ every day. The flame should be evenly distributed, and it should not lean on one side of the furnace wall or under the front or rear arch of the chain furnace. To prevent the chain grate from burning out, the chain grate should rotate regularly. The boiler water level should be kept at the lowest level during the furnace drying. Check frequently during furnace drying, and take remedial measures if cracks or pits are found.
-
WNS series gas-fired (oil-fired) skid-mounted hot water boilerLive Chat0.7-2.8 MW1.0 MPa
-
DZW series biomass-fired reciprocating grate steam boilerLive Chat15-35 t/h1.25 MPa / 1.6 MPa / 2.5 MPa
-
DZL series biomass-fired steam boilerLive Chat2-10 t/h1-2.5 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
Over the past two years, ZOZEN Boiler has supplied gas-fired steam boilers and related services to industrial customers in Venezuela. The applications include beverage production and papermaking. This article presents two projects: a 3 t/h WNS gas-fired steam boiler supplied to a Venezuelan beverage manufacturer and a 15 t/h WNS gas-fired steam boiler supplied to a local paper mill. Steam Supply for Beverage ProductionSteam is used in beverage production for blending, sterilization, equipment ...18 Aug 2026 -
Baijiu production is a continuous process. From grain steaming and fermentation to distillation, sterilization, and fermented-grain residue handling, many stages require a stable steam supply. As baijiu producers expand their operations, boiler systems need to provide sufficient steam while also adapting to different fuel conditions, changing loads, and environmental management requirements. In recent years, ZOZEN Boiler has developed steam boiler and auxiliary system solutions for baijiu produ...11 Aug 2026 -
A 10 TPH Boiler Delivered in 40 Days: The “ZOZEN Speed” Behind Yanjing Beer’s Letter of AppreciationRecently, Wuxi Zozen Boilers Co., Ltd. received a letter of appreciation from Yanjing Beer (Guilin Lijiang) Co., Ltd. In the letter, the customer expressed appreciation for ZOZEN Boiler’s responsiveness, coordination, and delivery support throughout the project. The customer also noted that ZOZEN helped resolve issues related to scheme adjustments, equipment access, and the delivery schedule. Letter of appreciation from Yanjing Beer (Guilin Lijiang) Co., Ltd. The letter was related to ...04 Aug 2026