Home Service FAQs Boiler basics What is the process and operation of low-pressure boiler furnace drying?

What is the process and operation of low-pressure boiler furnace drying?

14 Jan 2022

(1) The furnace drying time depends on the shape, structure and humidity of the furnace. It takes 4 ~ 7 days for small low-pressure boilers and 10 ~ 15 days for heavy furnace walls.

(2) First, bake with wood, on the ash hopper of the room furnace and the grate of the chain furnace, use small fire for natural ventilation within 2 ~ 3 hours. When the temperature of combustion chamber rises, the ventilation capacity will be improved, and the flue damper can be turned down a little. It is best to keep the exhaust temperature below 25℃ on the first day.

(3) The next day, the fire can be enlarged and placed in the center of the grate, and the water temperature in the boiler should not exceed 70℃. On the third day, coal is added to the fire, and it is gradually baked with coal.

(4) Starting from the fourth day, only use coal to burn, start the induced draft fan, increase the furnace temperature, and keep the negative pressure of the furnace at 5 ~ 10 Pa [0.5 ~ 1 mm H2O].

(5) The temperature of the low-pressure boiler should be slowly increased when drying, and the temperature rise should be controlled at 20 ~ 40℃ every day. The flame should be evenly distributed, and it should not lean on one side of the furnace wall or under the front or rear arch of the chain furnace. To prevent the chain grate from burning out, the chain grate should rotate regularly. The boiler water level should be kept at the lowest level during the furnace drying. Check frequently during furnace drying, and take remedial measures if cracks or pits are found.

Related FAQs View More
Related news View More
  • Heating Solutions, Local Support: ZOZEN Boiler’s Approach to Expanding in Vietnam
    Industrial heating upgrades can have a direct impact on a factory’s production schedule and operational stability. For manufacturers investing in new facilities or upgrading equipment in Vietnam, boiler selection involves more than fuel costs. Process temperatures, continuous heat supply, emission requirements, and long-term maintenance must all be taken into account. Whether transitioning from coal to natural gas or biomass, manufacturers need a heating solution tailored to their actual p...
    17 Nov 2026
  • Energy Costs and Stable Steam Supply Draw Attention as ZOZEN Boiler Provides Diverse Steam Solutions for Textile Enterprises Worldwide
    From spinning and weaving to dyeing, printing and heat setting, steam is required throughout multiple stages of textile production. As textile enterprises pay closer attention to energy costs, steam supply stability and emission requirements, boiler selection can no longer be based solely on rated evaporation capacity. Local fuel availability, production load, boiler room conditions and ongoing operation and maintenance also need to be considered. Recent textile projects served by ZOZEN Boiler ...
    10 Nov 2026
  • ZOZEN Boiler Supports Building Materials Projects in Hubei with Steam and Thermal Oil Solutions
    IntroductionIn Wuhan, Hubei Province, Hubei Hanjia New Materials Co., Ltd. and Wuhan Yiqingsheng Building Materials Co., Ltd. required thermal energy equipment for autoclave curing and continuous production-line heating, respectively. Based on the production processes, fuel conditions and site requirements of the two companies, ZOZEN Boiler supplied an 8 t/h DZL series biomass steam boiler and a 7.2-million-kcal YWW series biomass thermal oil boiler. The two projects use different heat-transfer ...
    03 Nov 2026

Find the Right Boiler For You

Name *

Email *

WhatsApp/WeChat

Products

Power/Capacity