What is the process and operation of low-pressure boiler furnace drying?
(1) The furnace drying time depends on the shape, structure and humidity of the furnace. It takes 4 ~ 7 days for small low-pressure boilers and 10 ~ 15 days for heavy furnace walls.
(2) First, bake with wood, on the ash hopper of the room furnace and the grate of the chain furnace, use small fire for natural ventilation within 2 ~ 3 hours. When the temperature of combustion chamber rises, the ventilation capacity will be improved, and the flue damper can be turned down a little. It is best to keep the exhaust temperature below 25℃ on the first day.
(3) The next day, the fire can be enlarged and placed in the center of the grate, and the water temperature in the boiler should not exceed 70℃. On the third day, coal is added to the fire, and it is gradually baked with coal.
(4) Starting from the fourth day, only use coal to burn, start the induced draft fan, increase the furnace temperature, and keep the negative pressure of the furnace at 5 ~ 10 Pa [0.5 ~ 1 mm H2O].
(5) The temperature of the low-pressure boiler should be slowly increased when drying, and the temperature rise should be controlled at 20 ~ 40℃ every day. The flame should be evenly distributed, and it should not lean on one side of the furnace wall or under the front or rear arch of the chain furnace. To prevent the chain grate from burning out, the chain grate should rotate regularly. The boiler water level should be kept at the lowest level during the furnace drying. Check frequently during furnace drying, and take remedial measures if cracks or pits are found.
-
WNS series gas-fired (oil-fired) skid-mounted hot water boilerLive Chat0.7-2.8 MW1.0 MPa
-
DZW series biomass-fired reciprocating grate steam boilerLive Chat15-35 t/h1.25 MPa / 1.6 MPa / 2.5 MPa
-
DZL series biomass-fired steam boilerLive Chat2-10 t/h1-2.5 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
From May 6 to 7, 2026, PALMEX JAKARTA 2026, the International Palm Oil Industry Equipment Exhibition, was held at JIEXPO in Jakarta, Indonesia. At booths 190 & 192, ZOZEN Boiler presented its boiler products and thermal energy solutions for industries such as palm oil processing. During the two-day exhibition, ZOZEN welcomed multiple groups of visitors, including existing clients and new prospects. Some new visitors returned to the booth several times for further discussions, and the overall...12 May 2026 -
ZOZEN Boiler has recently shipped a 10-ton WNS series heavy oil steam boiler to Ecuador, where it will support the production line of a local corrugated board packaging company. The project marks another step in ZOZEN’s expansion in Ecuador’s paper industry and reflects growing demand in South America for reliable steam supply, fuel adaptability, and after-sales support. ZOZEN WNS series heavy oil condensing steam boiler Stable steam supply matters in paper productionIn paper and...05 May 2026 -
From May 6 to 7, 2026, ZOZEN Boiler will participate in Palmex Indonesia 2026 at Jakarta International Expo (JIEXPO), Indonesia. ZOZEN Boiler will welcome visitors at Booth 190 & 192. As an industry event focused on the palm oil sector in Southeast Asia, the exhibition brings together companies involved in palm oil processing, supporting energy systems, and industrial equipment, offering ZOZEN Boiler a valuable opportunity to meet customers from Indonesia and surrounding markets. ZOZEN Bo...28 Apr 2026