Influencing factors of slagging on heating surface of boiler
(1) Ash characteristics of pulverized coal
Generally, the softening temperature ST of ash is used as the main indicator of slag formation. Coal with low ash melting point (ST<1200℃) is easy to slag. In addition, the slagging index also includes: silicon ratio, alkali-acid ratio, slagging index, limit viscosity and so on.
(2)Aerodynamic characteristics in the furnace
Improper air flow organization leads to flame center deviation, and the pulverized coal air flow flame adheres to the wall, causing local slagging of the water-cooled wall;
Improper air flow organization, forming flue gas retention vortex area and forming a reducing atmosphere (with CO), reducing the ash melting point and increasing the possibility of slagging.
Excess air coefficient: When the excess air in the furnace is too small, a reducing atmosphere may be generated, and the tendency of slagging will increase accordingly.
(3)Influence of boiler heat load
Boiler design heating load: The greater the heating load intensity, the higher the temperature of the burner area in the furnace, the coal ash reaches the molten state, and the possibility of slagging increases.
Boiler operation load: The higher the boiler operation heating load, the more heat is sent into the furnace and the greater the possibility of slagging.
(4)Influence of coal fineness
Coarse pulverized coal burns for a long time. When the proportion of coarse pulverized coal in the pulverized coal increases, it is easy to cause the flame to prolong and cause slagging on the heated surface at the outlet of the furnace.
Measures to prevent slagging on heated surface
(1) Prevent the temperature near the heated surface from being too high. Furnace design heating load intensity is reasonable, and reasonable furnace temperature is controlled; at the same time, sufficient heating surface is arranged to cool the flue gas to ensure that the molten ash has solidified before being close to the heating surface;
(2) Reasonably organize the airflow in the furnace, the burner layout is reasonable, the first and second air form a good airflow structure, ensure that the flame does not directly wash the heated surface; avoid excessively low air coefficient to produce a reducing atmosphere.
(3) Strengthen fuel management, do a good analysis of fuel ash composition and melting point, try to use design coal; avoid pulverized coal.
(4) Strengthen operation management, adjust combustion status in time, and blow dust and slag in time.
-
SZL series coal-fired steam boilerLive Chat6-35 t/h1-2.5 MPa
-
DHL series coal-fired steam boilerLive Chat20-75 t/h1.25-5.4 MPa
-
DZL series coal-fired steam boilerLive Chat2-10 t/h1-2.5 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat
-
On the thriving industrial land of Shandong, the continuous demand for thermal energy supply from enterprises drives the transformation of the boiler industry. With profound technical expertise and ongoing innovation, ZOZEN Boiler remains at the forefront of providing high-quality, adaptable boiler models for various industries. ZOZEN Boiler Provides Tailored Boiler Solutions for Shandong Industries Looking back, the cooperation projects with Shandong Luhua Group and Shandong...29 Jul 2025
-
In the industrial zone of Wen’an County, Xinghua Cable Co., Ltd. is making steady progress on its project with an annual production capacity of 11 million meters of wires, cables, and accessories, backed by an investment of RMB 520 million. Upon completion, the project is expected to create over 150 jobs and generate annual sales revenue of RMB 800 million, demonstrating promising prospects. As a key supplier of thermal energy equipment, ZOZEN Boiler is quietly supporting the development o...22 Jul 2025
-
On March 20, 2025, the Guizhou Jinyuan Zhijin “Replacing Small Units with Large Ones” Relocation Project (2×660 MW), under State Power Investment Corporation, successfully achieved the first ignition of its boiler. This project replaced traditional oil-fired ignition fuel with liquefied natural gas (LNG), setting a new precedent for employing clean energy in 660 MW ultra-supercritical “W” flame boilers. As a key equipment supplier for this project, ZOZEN Boiler prov...15 Jul 2025