Before the operation of oil-fired boiler, we should effectively adjust the heating system to make it conform to the actual working conditions. Moreover, what are the specific operating steps when adjusting the oil-fired boiler?
The first step is to add water to the oil-fired boiler. First open the water feeding valve, wait boiler's water level rising to the normal level, and close the water feeding valve.
It is not only the oil-fired boiler itself that need to be added water, but also the system. Open the system water feeding valve to add water, then observe the automatic exhausting conditions until the exhausting valve does not work, and finally close the water feeding valve. If the pressure of tap water does not meet the standards, a pump can be used to add water.
After the oil-fired boiler and system complete the water feeding, the low temperature operation of water pump can be set via the control box. However, before starting the pump, open all the valves except the water feeding valve. Meanwhile, open the open/close device, hydraulic tube and exhausting valve to exhaust the air and observe boiler's water level at the same time.
If the water level rises significantly, the resistance control valve should be turned down properly until the water level stops rising; if the water level drops, it indicates that the system is not be added enough water, so keep adding water to the oil-fired boiler until the water level stops dropping. After the water level of oil-fired boiler is adjusted to the normal, shut off the water pump and check whether the parts like open/close device and back-pressure valve are normal.
The checking method is also very simple to observe whether the water level of oil-fired boiler is rising. If the water level rises, it indicates the valves are not fully closed. There will be the sound of water flow when putting the ear closely on the open/close device and back-pressure valve. If there is something wrong with the open/close device, check the valve. If there is something blocked, remove it as soon as possible.
-
WNS series gas-fired (oil-fired) steam boilerLive Chat1-20 t/h0.7-2 MPa
-
WNS series gas-fired (oil-fired) hot water boilerLive Chat0.7-14 MW0.7-1.25 MPa
-
SZS series gas-fired (oil-fired) steam boilerLive Chat2-110 t/h1.25-5.3 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat
-
On March 20, 2025, the Guizhou Jinyuan Zhijin “Replacing Small Units with Large Ones” Relocation Project (2×660 MW), under State Power Investment Corporation, successfully achieved the first ignition of its boiler. This project replaced traditional oil-fired ignition fuel with liquefied natural gas (LNG), setting a new precedent for employing clean energy in 660 MW ultra-supercritical “W” flame boilers. As a key equipment supplier for this project, ZOZEN Boiler prov...15 Jul 2025
-
Under the Belt and Road Initiative, economic and cultural ties between China and Pakistan are growing ever stronger, with more frequent exchanges between businesses from both countries. Recently, ZOZEN Boiler’s Sales Director led a team to visit Pakistan, where they held a meaningful meeting with Kohinoor Mills, a leading local textile company. During the gathering, both sides exchanged honorary plaques and thoughtful gifts—gestures that not only celebrate past collaborations but als...08 Jul 2025
-
In the first half of 2025, as a leading enterprise in China’s industrial boiler sector, ZOZEN Boiler has actively expanded into global markets with an international vision and innovative drive. The company made impressive appearances at the Pakistan Textile Exhibition and the Russian HEAT&ELECTRO MACHINERY Expo, continuously expanding its brand influence and bringing efficient, environmentally friendly energy solutions to customers worldwide, contributing to the green upgrade of the in...01 Jul 2025