What aspects are included in the system commissioning before the operation of oil-fired boiler?
Before the operation of oil-fired boiler, we should effectively adjust the heating system to make it conform to the actual working conditions. Moreover, what are the specific operating steps when adjusting the oil-fired boiler?
The first step is to add water to the oil-fired boiler. First open the water feeding valve, wait boiler's water level rising to the normal level, and close the water feeding valve.
It is not only the oil-fired boiler itself that need to be added water, but also the system. Open the system water feeding valve to add water, then observe the automatic exhausting conditions until the exhausting valve does not work, and finally close the water feeding valve. If the pressure of tap water does not meet the standards, a pump can be used to add water.
After the oil-fired boiler and system complete the water feeding, the low temperature operation of water pump can be set via the control box. However, before starting the pump, open all the valves except the water feeding valve. Meanwhile, open the open/close device, hydraulic tube and exhausting valve to exhaust the air and observe boiler's water level at the same time.
If the water level rises significantly, the resistance control valve should be turned down properly until the water level stops rising; if the water level drops, it indicates that the system is not be added enough water, so keep adding water to the oil-fired boiler until the water level stops dropping. After the water level of oil-fired boiler is adjusted to the normal, shut off the water pump and check whether the parts like open/close device and back-pressure valve are normal.
The checking method is also very simple to observe whether the water level of oil-fired boiler is rising. If the water level rises, it indicates the valves are not fully closed. There will be the sound of water flow when putting the ear closely on the open/close device and back-pressure valve. If there is something wrong with the open/close device, check the valve. If there is something blocked, remove it as soon as possible.
-
WNS series gas-fired (oil-fired) steam boilerLive Chat1-20 t/h0.7-2 MPa
-
WNS series gas-fired (oil-fired) hot water boilerLive Chat0.7-14 MW0.7-1.25 MPa
-
SZS series gas-fired (oil-fired) steam boilerLive Chat2-110 t/h1.25-5.3 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
South America is rich in agricultural and energy resources and has a diverse manufacturing base. Industries such as papermaking, packaging and sugar processing are upgrading their production equipment as market and environmental requirements evolve. For these companies, a boiler is more than a steam source. Its performance affects production continuity, fuel consumption, process quality and emissions management. Through projects in Venezuela, Brazil and Ecuador, ZOZEN Boiler has continued to ex...21 Jul 2026 -
As the 2026 FIFA World Cup brings the United States, Mexico and Canada into the international spotlight, attention is once again turning to the cities, industries and communities across North America. Away from the stadiums, manufacturing plants, beverage production lines and automotive component facilities continue their daily operations, providing steady support for local economies. ZOZEN Boiler’s WNS Series Serving Industrial Projects in North America In these less visible parts of ...14 Jul 2026 -
At the production site of a pharmaceutical company in Shanghai, a ZOZEN gas-fired steam boiler commissioned in 2010 has been operating steadily for 16 years. For this established pharmaceutical company, founded in 1995, the steam system is closely related to production rhythm, process coordination, and on-site operation support. Whether the equipment can maintain stable operation over the long term directly affects the continuity of daily production. Time is a practical test, and the continuous ...07 Jul 2026