What aspects are included in the system commissioning before the operation of oil-fired boiler?
Before the operation of oil-fired boiler, we should effectively adjust the heating system to make it conform to the actual working conditions. Moreover, what are the specific operating steps when adjusting the oil-fired boiler?
The first step is to add water to the oil-fired boiler. First open the water feeding valve, wait boiler's water level rising to the normal level, and close the water feeding valve.
It is not only the oil-fired boiler itself that need to be added water, but also the system. Open the system water feeding valve to add water, then observe the automatic exhausting conditions until the exhausting valve does not work, and finally close the water feeding valve. If the pressure of tap water does not meet the standards, a pump can be used to add water.
After the oil-fired boiler and system complete the water feeding, the low temperature operation of water pump can be set via the control box. However, before starting the pump, open all the valves except the water feeding valve. Meanwhile, open the open/close device, hydraulic tube and exhausting valve to exhaust the air and observe boiler's water level at the same time.
If the water level rises significantly, the resistance control valve should be turned down properly until the water level stops rising; if the water level drops, it indicates that the system is not be added enough water, so keep adding water to the oil-fired boiler until the water level stops dropping. After the water level of oil-fired boiler is adjusted to the normal, shut off the water pump and check whether the parts like open/close device and back-pressure valve are normal.
The checking method is also very simple to observe whether the water level of oil-fired boiler is rising. If the water level rises, it indicates the valves are not fully closed. There will be the sound of water flow when putting the ear closely on the open/close device and back-pressure valve. If there is something wrong with the open/close device, check the valve. If there is something blocked, remove it as soon as possible.
-
WNS series gas-fired (oil-fired) steam boilerLive Chat1-20 t/h0.7-2 MPa
-
WNS series gas-fired (oil-fired) hot water boilerLive Chat0.7-14 MW0.7-1.25 MPa
-
SZS series gas-fired (oil-fired) steam boilerLive Chat2-110 t/h1.25-5.3 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
On the edge of the tropical jungles of Sumatra, Indonesia, the hum of machinery blends with the scent of palm fruit, painting a busy picture of the local palm oil processing industry. As a key global production base, Indonesian oil processing enterprises have a high dependency on reliable thermal energy supply. Booming Oil Processing Industry in Indonesia Recently, Wuxi ZOZEN Boiler Co., Ltd. ("ZOZEN Boiler") successfully delivered and commissioned a 15 t/h SZL series coal-fired steam boiler...03 Feb 2026 -
As clean heating upgrades continue to accelerate across northern China, high-efficiency and environmentally compliant heating equipment has become essential to ensuring winter heating security while supporting the country’s carbon reduction goals. In Tianjin, several large district heating companies have independently selected the same core solution — the ZOZEN SZS series gas-fired hot water boiler — delivering stable heat throughout the winter while contributing to improved ai...27 Jan 2026 -
The Regulations on the Administration of Rare Earths, effective from October 1, 2024, are accelerating the rare earth industry’s standardized and intensive transformation under the framework of resource protection, compliant governance, and green development. As demand for rare-earth permanent magnet materials from sectors such as new energy vehicles, wind power, and intelligent manufacturing stabilizes and improves, industry sentiment is rebounding. As the “World Capital of Rare Ear...20 Jan 2026