Service is more than a slogan, documentary of ZOZEN after-sales engineer thermal oil heater project commissioning in Inner Mongolia
The thermal oil heater belongs to special equipment. The commissioning of the new heater is very significant in order to ensure stable operation in a long term, and it is also highly dangerous, which requires high technical experience for the commissioning person. After-sales engineer in ZOZEN Boiler has already worked in after-sales career for decades with abundant experience and super technology. They offered outstanding service this time when serving to Wuhai Shilian Environmental Protection Technology Co., Ltd. on thermal oil heater project.
Wuhai Shilian Environmental Protection Technology Co., Ltd., located in Xilaifeng Project Area Hainan Industrial Park, Inner Mongolia, is a chemical enterprise focused on producing phenol and related products. Wuhai Shilian Fine Chemical Industrial Park project started in 2019, and it planned to build a 20,000 tons annual production capacity of phenol series product technology transformation project with a total investment of RMB 320 million. The boiler is a piece of important thermal energy equipment on the production line. Wuhan Shilian eventually selected ZOZEN YQL series thermal oil heater after nationwide comparisons and inspections.
This project was a key industrial project in the spring of 2020 in Wuhai City, Inner Mongolia, which was highly expected by the local government. The various work, including the installation of the thermal oil heater, was still carried out smoothly with full support of the local epidemic prevention and control department during COVID-19. when the boiler was about to enter the commissioning phase, and ZOZEN Boiler immediately dispatched after-sales engineers to Wuhai City, Inner Mongolia to commission the new boiler.
ZOZEN Thermal Oil Heater for Wuhai Shilian Project Base
The thermal oil heater is a boiler that transfers heat through an organic heating carrier as a heating medium. Different from the gas-fired boiler commissioning, in addition to the the normal system inspection and load commissioning, the thermal oil heater also need to dehydrate water and exhaust steam, therefore, the difficulty and danger are both dramatically increased.
Thermal Oil Heater Oil Storage Tank
The main work of the thermal oil heater commissioning is to heat up, and the heating up process follows the principle of "one slow and two stops". As per the thermal oil heating up curve, "one stop" needs to be done when the oil temperature reaches about 100℃ and maintaining the temperature range from 95℃ to 100℃. The specific temperature control is both decided by the experience of the after-sales engineer and on-site situation. The water contained in the heater system is vaporized at 100℃ at this stage, and discharged through the high level tank vent pipe and the auxiliary exhaust pipe, so as to achieve the purpose of dehydration and steam exhaust. The end time of this process is mainly decided by observing the jitter of the pressure gauge. If the pressure gauge shakes intensely, then continue on operating the heat preservation to keep up the work of dehydration and steam exhaust. The shortest time of the whole process usually takes 3 days.
After the dehydration and steam exhaust of the boiler, the temperature is gradually increased to about 210-230 ℃, that reaches the step of the "second stop", which is the oil boiling stage of the thermal oil heater. The purpose is to avoid potential safety hazards by removing impurities in the thermal oil. It should be noted that if there still has either water or steam in the boiler system at this stage, it might cause oil injection in the high-level expansion tank, and even worse it may cause deflagration in some serious cases. So, the word "slow" entirely runs through the heating process. The oil temperature needs to be immediately reduced to safety range once the operation is incorrect. The step is repeated until the temperature finally reaches the working degree. Therefore, the commissioning of the entire thermal oil heater takes at least half a month.
Chen Wei, the after-sales engineer from ZOZEN Boiler, completed the initial start-up and commissioning after 4 days of intensive work. He pointed out the problems during the installation process of Wuhai Shilian and found few leaks in the installation pipeline. And moreover, he recommended on replacing the actuator of flow adjusting valve and commissioning of boiler loading can only be carried out later. The project leader highly expressed recognition and praise on the professionalism and responsibilities of ZOZEN’s after-sales engineers.
The service commitment is more than a slogan, an idea or an advertisement. Highly obeying Four-Full service standards, ZOZEN Boiler will continue to actively cooperate with users under a careful attitude to complete the commissioning of thermal oil heater to ensure the project of Wuhai Shilian could be enforced orderly.
-
YQ(Y)W series gas-fired/oil-fired horizontal thermal oil heater1400-14000 kW0.8-1.0 MPa
-
YQ(Y)L series gas-fired/oil-fired thermal oil heater7000-29000 kW0.8-1.0 MPa
View More
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat
Request a Quote
Inquiry-
As an energy company, Sotratech limitee's customers spread around Mauritius, the Indian Oceana, Africa and many other regions. As the heart device of the energy engineering, Sotratech limitee attached much attention on the selection of boilers. The boilers in domestic market in Mauritius couldn't meet the demands of the company, so the company decided to look for partners in China. The bidding document attracted a large number of well-known enterprises for bidding. How did ZOZEN stand out from the fierce competition? ZOZEN recommended YQW series thermal oil heater on the basis of the project requirements of Sotratech limitee. This kind of thermal oil heater could be equipped with different waste heat recovery devices to meet the needs of different users. In addition, the thermal oil heater is highly appreciated by customers with its packaged structure and easy installation. Not surprisingly, Sotratech limitee was also deeply impressed by this series of thermal oil heater.12 Mar 2019
-
Recently, ZOZEN has again won the favor of textile industry giant Kay & Emms in Pakistan due to its high quality products and excellent service. The textile industry is the pillar of the Pakistani economy. In the textile industry, the processes of dyeing, drying, slashing, printing and dyeing, etc. Have certain requirements for temperature. A boiler is regarded as one piece of the important equipment in the production line of textile enterprises. Kay & Emms (Pvt) Ltd. is a textile enterprise with whole industrial chain production capacity. Its business includes knitting, dyeing, embroidering, cutting and splicing of fabrics and finishing and packaging of garments.19 Nov 2019
-
With the acceleration of the industrialization process, the problem of water pollution needs to be solved urgently. Water purification agent manufacturers have played a huge role in eliminating water pollution. ZOZEN and many water purification materials manufacturers work together to make efforts for the clean ecological environment. Among them, Chongqing Lanjie Guangshun Water Purification Materials Co., Ltd. is a subsidiary of Chongqing Lanjie Tap Water Materials Co., Ltd., which produces polyaluminum chloride water treatment agent with an annual output of 50,000 tons.17 Oct 2019
Find the Right Boiler For You
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat