How to start a hot water boiler?
1、A hot water boiler should be thoroughly inspected at first, including the accessory pipeline. Close the drain valve and open the gauge cock to discharge the air in the boiler.
2、Slowly pour the treated water into the hot water boiler while the inlet water temperature is generally not higher than 40℃. Keep a close eye on the water level as the pressure increases and turn off the feed water when the level of water inside the gauge glass is stable.
3、Open the boiler gate and ignite the firewood or other combustible materials (iron nails are strictly prohibited) which are laid flat in front of the grate. Turn up the flue gas valve to enhance natural ventilation until the materials burn, then intermittently turn on the induced draft fan and manually add the coal after the sufficient combustion. Observe the combustion situation and properly poke the fire. Until the coal can combust continuously, adjust the induced air draft to ensure the negative pressure in the hearth is between 0.1-0.2 MPa and gradually realize the normal combustion.
4、The ignition temperature should slowly increase to avoid excessive thermal stress due to uneven heating of each part. The first ignition to heat the cold furnace to the working pressure is better in 3-4 hours. Except for the urgent requirement of gas, the cold furnace ignition time should be over 2 hours, and the hot furnace should be over 1 hour.
5、Keep a close eye on the water level as the pressure increases. Open the drain valve when it exceeds the highest water level.
6、When steam emerges from an opened safety valve, it should be closed and the pressure gauge, elbow and water level gauge should be flushed. When the steam pressure rises to 0.2-0.3 MPa, check whether the manhole cover, hand hole cover and the drain valve are leaking or not. If there is any leakage, tighten the bolts.
7、When the steam pressure in the boiler gradually rises, check whether there are special noises in the hot water boiler. If there is, immediately shut down for inspection. Continue it after solving the problems.
-
WNS series gas-fired (oil-fired) hot water boilerLive Chat0.7-14 MW0.7-1.25 MPa
-
SZS series gas-fired (oil-fired) hot water boilerLive Chat7-116 MW1-1.6 MPa
-
DZL series coal-fired hot water boilerLive Chat1.4-7 MW0.7-1.25 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
ZOZEN Boiler: Empowering Pakistan’s Textile Industry with Technology and Service for a Green UpgradeAs the pillar of Pakistan’s economy, the textile industry plays a crucial role in the national economic landscape and manufacturing system. Its energy needs and environmental transformation have long been central to industry development. Having cultivated the Pakistan market for years, ZOZEN Boiler has become a trusted partner for local textile enterprises through customized biomass energy solutions, mature reciprocating grate technology, and a localized service system—delivering a c...11 Nov 2025 -
WISE New Material Taizhou Co., Ltd. (hereinafter referred to as “WISE New Material”) is an enterprise focusing on the R&D, production, and sales of electronic functional tapes, special high-performance protective films, power battery materials, and semiconductor new materials. As application scenarios continue to expand, the production process has put forward stricter requirements for temperature control and continuous equipment operation. In 2023, WISE New Material chose the YQW...04 Nov 2025 -
On October 23, the three-day 2025 Russia Moscow Industrial Boiler and Heat Exchange Exhibition (Heatpower Expo) concluded successfully. With a meticulously planned participation strategy and a highly professional team, ZOZEN Boiler completed this overseas showcase smoothly, engaging in in-depth exchanges with customers from multiple sectors including energy, chemicals, building materials, and food, fully demonstrating the company’s comprehensive strengths in clean, high-efficiency technolo...28 Oct 2025