How to start a steam boiler?
1、Ensure that the vent valve on the boiler is open and check there is no pressure in the boiler. Check that the steam stop valve is closed. Check that all the valves for fuel are open, and let the fuel circulate through the system until it comes to the temperature required by the manufacturer recommendation.
2、Check whether the power supply, natural gas, instrument air, etc. meet the boiler operation requirements.
3、Check and open the feed water valves to the boiler and fill the water inside the boiler drum to just above the low water level. This is done because it is not possible to start the boiler below the low water level due to safety features that prevent the boiler from starting. Also, the level is not filled much because if filled too much, the water inside the boiler might expand and over pressurize the boiler. The boiler feed water level should be around 50%.
4、Start the boiler in automatic mode. The burner fan will start the purging cycle which will remove any gases present in the furnace by forcing it out through the funnel.
5、After the pre-set purge time the pilot burner will ignite. The pilot burner consists of two electrodes, through which a large current is passed, via the transformer, producing the spark between the electrodes. The pilot burner is supplied with diesel oil and when the oil passes over, the former ignites.
6、Realize the gas supply by opening the pressure reducing valve of the natural gas pipeline. Replace it with the vent valve for 2 to 3 minutes, and then close the vent valve after the steam starts coming outside.
7、Check the combustion chamber from the sight glass to ensure the burner has lit and the flame is satisfactory.
-
SZS series gas-fired (oil-fired) steam boilerLive Chat2-110 t/h1.25-5.3 MPa
-
WNS series gas-fired (oil-fired) steam boilerLive Chat1-20 t/h0.7-2 MPa
-
SZL series coal-fired steam boilerLive Chat6-35 t/h1-2.5 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat
-
April 12–14, 2025 – The 29th Pakistan Textile Asia International Exhibition and Conference was grandly held at the Karachi Expo Centre. As a pivotal event in the global textile industry, this exhibition attracted renowned enterprises from around the world. ZOZEN Boiler, a leading industrial boiler manufacturer, was invited to participate once again. Showcasing its flagship product—the 10–40 ton three-drum biomass boiler—ZOZEN engaged in in-depth exchanges with Pakis...15 Apr 2025
-
In recent years, with the rapid development of the pharmaceutical industry, enterprises have raised higher demands for the stability, environmental performance, and efficiency of production equipment. As a renowned industrial boiler manufacturer in China, ZOZEN Boiler has become a trusted partner for many pharmaceutical companies thanks to its high-quality products and outstanding service. Among these collaborations, the partnership with Sinopharm Weiqida Pharmaceuticals Co., Ltd. stands out as ...08 Apr 2025
-
Pakistan, the world’s fourth-largest cotton producer and third-largest consumer, holds a pivotal position in the global cotton textile market. LUCKY TEXTILE MILLS LIMITED (hereafter referred to as LUCKY TEXTILE), with over 40 years of industry expertise, stands as a cornerstone of Pakistan’s textile sector and a key driver in steering the industry toward greener, more sustainable practices. Textile Leader LUCKY TEXTILE Chooses ZOZEN Biomass Boilers ZOZEN Boiler, a pioneer in the ...01 Apr 2025