What are the installation requirements for the circulating pump of the thermal oil heater?
The installation requirements for the circulating pump of the thermal oil heater
1) Quantity. The circulating system should include at least two sets of heat oil circulating pumps. On is a working pump and the other is a standby pump.
2) Head. The rate of flow and head of the circulating pump must ensure the flow velocity of heat medium oil in the thermal oil heater. The flow velocity on the radiation heating surface should not be less than 2 meters per second, and the flow velocity on the convention heating surface should not be less than 1.5 meters per second.
3) Power. There should be a backup power supply or other equipment in the boiler room to ensure the normal operation of the circulating pump in the event of a power failure.
4) Filter. The filter should be installed at the inlet of the circulating pump and should be cleaned regularly.
5) Filling pump. The appearance, installation size and basic conditions of the filling pump should refer to the product documents and installation instructions.
-
YQ(Y)W series gas-fired/oil-fired horizontal thermal oil heaterLive Chat1400-14000 kW0.8-1.0 MPa
-
YQ(Y)L series gas-fired/oil-fired thermal oil heaterLive Chat7000-29200 kW0.8-1.0 MPa
-
YLW series coal-fired thermal oil heaterLive Chat2800-29200 kW0.8-1.0 MPa
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat

-
Behind industrial manufacturing often lies an invisible thermal energy lifeline. Whether boiling syrup, synthesizing chemical materials, or pressing new energy security materials, every physical and chemical change on the production line has strict requirements for the temperature, pressure, and continuity of thermal energy. When green biomass energy enters these vastly different manufacturing workshops, how can various forms of pellets, wood blocks, or straw be converted into the "precise temp...08 Sep 2026 -
Recently, a special equipment inspection team visited Wuxi Zozen Boilers Co., Ltd. for an inspection and guidance session. Mr. Zhang Guoping, General Manager of ZOZEN Boiler, together with representatives from relevant departments, participated in the inspection and discussions. The meeting focused on special equipment production quality management, the implementation of safety responsibilities, manufacturing process control, and documentation management. Special Equipment Inspection Team Con...25 Aug 2026 -
At a local paper manufacturing company in Egypt, a ZOZEN WNS Series 6 t/h gas-fired steam boiler has been supplied as part of an export project. The Egyptian paper mill uses natural gas as the boiler fuel to meet the process steam requirements of paper production. The project also includes technical documents and a product solution prepared in accordance with ASME and CE certification requirements. Paper manufacturing is a continuous industrial process. Steam is involved in several stages, incl...01 Sep 2026