Prepare relevant technical data, including technical data of boiler manufacture and installation, boiler use registration data, boiler operation records, water quality test records, repair and modification records, accident records and previous inspection reports;
Strictly control the operating pressure of the environmental thermal oil heater, and do not exceed the specified range. Once there is a trend of exceeding the specified upper limit, immediate measures should be taken.
The economizer of condensing gas-fired boiler can be installed in the flue of the current CFB boiler, to recovery the energy from the high-temperature flue gas, in order to reduce the fuel consumption. Also, the economizer helps to absorb the air pollutants such as the NOx and sulfur dioxide.
Removal of metallic scale and corrosion products generally requires chemical cleaning. Acid or chelant cleaning procedures vary greatly depending on individual circumstances. Chemical cleaning can improve the boiler heat rate and reduce the number of tube failures. It typically improves the stability of boiler chemistry.
A hot water boiler should be thoroughly inspected at first, including the accessory pipeline. Close the drain valve and open the gauge cock to discharge the air in the boiler.
The installation contents of boiler body pipeline are as follows:
1) Connection between water supply console and economizer header;
2) Connection between economizer and inlet pipe from economizer outlet to drum;
3) Connection between the main pipe and branch pipe of the drum drop and each lower header of the water wall;
4) Connection of steam guide pipe between each water wall header and steam drum;
5) Connection of superheated steam pipe between outlet header of low-temperature superheater...
All boiler pipes have been installed and passed the hydrostatic test.
The furnace wall masonry and insulation work have all ended and has been qualified.
The flue gas duct has been installed and insulated, and the induced draft fan has been installed and debugged to be qualified and can be put into operation.
All the thermal and electrical instruments required for boiler drying have been installed and verified to be qualified.
Mortar samples have been placed on both sides of the middle par...
Boiler feedwater treatment system includes two parts: pre-desalination system and ion exchange desalination system.
The pre-desalination system includes ultrafiltration system, reverse osmosis system, dosing system, chemical cleaning system, compressed air system, etc.
The ion exchange desalination system includes ion exchange system, acid-base regeneration system, compressed air system, wastewater neutralization treatment system, etc.
The boiler feedwater treatment methods ar...