What are the conditions for boiler furnace?
03 Sep 2021
- All boiler pipes have been installed and passed the hydrostatic test.
- The furnace wall masonry and insulation work have all ended and has been qualified.
- The flue gas duct has been installed and insulated, and the induced draft fan has been installed and debugged to be qualified and can be put into operation.
- All the thermal and electrical instruments required for boiler drying have been installed and verified to be qualified.
- Mortar samples have been placed on both sides of the middle part of superheater as required.
- Wood, diesel oil, coal and various tools (including inspection and on-site lighting, etc.) For boiler drying have been prepared.
- All facilities used for boiler furnace are installed, and all other temporary facilities unrelated to furnace are removed, and the site is cleaned up.
- All the stokers have been trained and qualified, and arranged on duty watch, and arrived on time as required.
Related FAQs
View More
Related products
View More
-
WNS series gas-fired (oil-fired) steam boilerLive Chat1-20 t/h0.7-2 MPa
-
SZS series gas-fired (oil-fired) steam boilerLive Chat2-110 t/h1.25-5.3 MPa
-
WNS series gas-fired (oil-fired) hot water boilerLive Chat0.7-14 MW0.7-1.25 MPa
By boiler medium
By boiler structure
-
Email us
-
WhatsApp: +86 18861589035
WeChat: +86 13506150756
Live Chat
Related news
View More
-
On the thriving industrial land of Shandong, the continuous demand for thermal energy supply from enterprises drives the transformation of the boiler industry. With profound technical expertise and ongoing innovation, ZOZEN Boiler remains at the forefront of providing high-quality, adaptable boiler models for various industries. ZOZEN Boiler Provides Tailored Boiler Solutions for Shandong Industries Looking back, the cooperation projects with Shandong Luhua Group and Shandong...29 Jul 2025
-
In the industrial zone of Wen’an County, Xinghua Cable Co., Ltd. is making steady progress on its project with an annual production capacity of 11 million meters of wires, cables, and accessories, backed by an investment of RMB 520 million. Upon completion, the project is expected to create over 150 jobs and generate annual sales revenue of RMB 800 million, demonstrating promising prospects. As a key supplier of thermal energy equipment, ZOZEN Boiler is quietly supporting the development o...22 Jul 2025
-
On March 20, 2025, the Guizhou Jinyuan Zhijin “Replacing Small Units with Large Ones” Relocation Project (2×660 MW), under State Power Investment Corporation, successfully achieved the first ignition of its boiler. This project replaced traditional oil-fired ignition fuel with liquefied natural gas (LNG), setting a new precedent for employing clean energy in 660 MW ultra-supercritical “W” flame boilers. As a key equipment supplier for this project, ZOZEN Boiler prov...15 Jul 2025